How Did SIRRL’s Project Kea Get Included Into Fast-Track
While South Island Resource Recovery Ltd (SIRRL) lodged an application on 1 May 2024 to have its Project Kea waste-to-energy proposal included in the Government’s Fast-track legislation, it was not the only waste incinerator project seeking a place on the list. Global Contracting Solutions Ltd (GCSL) also lodged an application for its proposed Paewira waste-to-energy project at Te Awamutu. The two proposals were not identical, but they had obvious similarities in their technology, scale and likely effects. More importantly for what followed, they travelled essentially the same path through the Fast-track selection process. Both went through the Ministry for the Environment’s initial process to determine whether their applications were complete. Both then went before the Government’s independent Fast-track Projects Advisory Group. And both were recommended for inclusion as Schedule 2 projects. At that point, there was remarkably little separating the status of the two proposals. Whatever differences existed between the projects themselves, neither had been rejected by the independent assessment process. Both had made it through the Ministry’s completeness check, both had been assessed by the Advisory Group and both had emerged with a recommendation for inclusion. Then something changed. When the Government announced its final list, Project Kea was there. GCSL was not. That raises some obvious questions. If both proposals had reached essentially the same point in the process, who decided that SIRRL should proceed while GCSL should not? What distinguished one from the other at that final stage? And what advice or information was used to make that decision? Why Waste Waimate has spent the past few months trying to answer those seemingly simple questions. It has proved considerably more difficult than it should have been. A perplexing answer Our first questions went to then Environment Minister Penny Simmonds. We asked a fairly straightforward question: given the similar technology, scale and likely effects of the two proposals, why had SIRRL’s project been included in Fast-track while GCSL’s had not? The answer we received was surprising. Simmonds told us GCSL had not lodged a Fast-track application. That was rather perplexing, given that her own Ministry had assessed GCSL’s Fast-track application for completeness as part of the process. The Minister’s response had to be challenged and corrected, but correcting that answer still did not tell us why the two projects had received different outcomes. Our attention therefore turned to the Minister responsible for RMA Reform, Chris Bishop. What followed has been months of OIA requests and correspondence attempting to pin down answers to essentially the same questions we started with. Why was Project Kea included when GCSL was not? Who made that decision? And what advice or information was available to the person who made it? These should not be particularly difficult questions to answer. They have nevertheless proved remarkably difficult to get clear answers to. After the Advisory Group One thing has become much clearer through the process. The independent Advisory Group did not make the decision that separated SIRRL from GCSL. It couldn’t have, because it recommended both. Bishop subsequently clarified through the OIA process that officials did not make the final project-selection decisions either. Those decisions were made by Ministers through the Government’s subsequent decision-making process. That is significant because it identifies the point at which the paths of the two projects diverged. Referring us back to the Advisory Group cannot explain why Project Kea was ultimately selected while another waste-to-energy proposal recommended by the same group was not. Whatever caused the different outcomes happened after the Advisory Group had finished its work. The Government’s own published Cabinet material gives us a much better idea of who was responsible for that next stage. Responsibility for project selection had been delegated between three Ministers according to the sectors the projects fell within. Chris Bishop was responsible for Housing/Land Development and Infrastructure, excluding transport and energy. Simeon Brown was responsible for Transport and Energy, while Shane Jones was responsible for Mining, Quarrying, Aquaculture and Farming. Project Kea was listed under Housing/Land Development. On the information currently available, that places Project Kea within Bishop’s delegated responsibility. We have been careful about this point. We do not have a document saying, in those exact words, “Chris Bishop decided to include Project Kea.” But Bishop has now been provided with several opportunities to tell us if somebody else made that decision. He hasn’t. Instead, the available Cabinet material identifies Bishop as the Minister responsible for the category under which Project Kea was selected. That brings us back to the harder question: why? What changed? At the end of the Advisory Group process, both SIRRL and GCSL had been recommended. At the end of the Ministerial selection process, SIRRL was in and GCSL was out. Something therefore happened between those two points. The published Cabinet material tells us that Ministers had more information available to them than simply the Advisory Group’s recommendations. It refers to further cross-agency or supplementary advice from officials and says that, where Ministers diverged from the Advisory Group’s recommendations, supplementary advice assessing projects against Government priorities informed those decisions. That would appear to be exactly the sort of information capable of explaining what happened to SIRRL and GCSL. Officials may have identified some significant advantage in Project Kea, or a problem with GCSL. The projects may have performed differently when considered against wider Government priorities. Ministers may have received other information that was not decisive during the Advisory Group process. Or a Minister may simply have exercised discretion and chosen one over the other. The problem is that, after months of asking, we still don’t know. Over a series of OIA requests and follow-up correspondence, Bishop has been given repeated opportunities to provide the missing information or explain where it can be found. We have sought the identity of the decision-maker, the authority under which the decision was made, assessments, recommendations, advice, briefings and information explaining the different treatment of SIRRL and GCSL. Eventually Bishop’s office gave what appears to be its final position:
How Did SIRRL’s Project Kea Get Included Into Fast-Track Read More »










